STATE OF NORTH DAKOTA PUBLIC SERVICE COMMISSION Otter Tail Power Company Case No.

STATE OF NORTH DAKOTA
PUBLIC SERVICE COMMISSION
Otter Tail Power Company
Case No. PU-21-376
Transmission Facility Cost Recovery (2022)
Rates
NOTICE OF OPPORTUNITY FOR HEARING
October 6, 2021
On September 16, 2021, Otter Tail Power Company (OTP) filed an annual update under its Transmission Facility Cost Recovery Rider (TCRR) tariff. The proposed rate update for 2022 includes the costs for three new transmission projects, updated costs for previously approved transmission projects, Midcontinent Independent System Operator revenues and expenses, Southwest Power Pool revenues and expenses, and a true-up amount from the current rate. The increase for a residential customer using 1,000 kWh per month would be $0.41 per month. The issues to be considered in this proceeding are:
1. Whether the proposed rate adjustment complies with OTP's tariff,
2. Whether the incurred costs for new or modified electric transmission facilities are reasonable and prudent, and
3. Whether the incurred costs are eligible for recovery through the TCRR.
Those interested are invited to comment on the application in writing. Persons desiring a hearing must file a written request identifying their interest in the proceeding and the reasons for requesting a hearing. Comments and requests for hearing must be received by November 20, 2021. If deemed appropriate, the Commission can determine the matter without a hearing.
For more information contact the Public Service Commission, State Capitol, Bismarck, North Dakota 58505, 701-328-2400 or Relay North Dakota 1-800-366-6888 TTY. If you require any auxiliary aids or services, such as readers, signers, or Braille materials, please notify the Commission 24 hours in advance.
PUBLIC SERVICE COMMISSION
Randy Christmann, Commissioner
Julie Fedorchak, Chair
Brian Kroshus, Commissioner