ADVERTISEMENT

ADVERTISEMENT

Interstate 29 raising project making major strides

Project that has involved shutting down an interstate exit to Hickson and Oxbow this summer should be done in about two months or the end of September as construction continues on schedule

072522.N.FF.CONSTRUCTION12
Work continues south of Fargo as crews have finished concrete paving of about 1.25 miles of the newly raised interstate in the southbound lanes. The construction is part of the Fargo Moorhead flood control diversion project to keep the interstate and nearby county roads out of the flood plain during major floods.
David Samson/The Forum
We are part of The Trust Project.

Editor's note: This is the 12th in a series of articles updating construction projects, road detours and lane closures in the Fargo-Moorhead area.

OXBOW — The County Road 18 overpass bridge deck over Interstate 29 is poured and concrete paving is underway on the newly raised interstate just south of Fargo.

The project, which is part of the Fargo-Moorhead flood diversion, is on schedule.

Army Corps of Engineers Resident Engineer Mathew Andersen and Project Engineer Troy Tooz, who are overseeing the work by Industrial Builders of West Fargo, are pleased with the progress and said it's been a nice summer for work.

Detours and lane closures in the area stem from construction of the new overpass bridge, raising County Roads 18 and 81 as well as tie-in levees for the Oxbow and Hickson flood-control system.

ADVERTISEMENT

Those closures should be over by the end of September, Andersen and Tooz said.

Depending on weather, the bridge, on and off ramps to I-29 and newly reconstructed County Roads 18 and 81 should be completed by then.

072522.N.FF.CONSTRUCTION12
Work continues on building the guardrails on the County Road 18 overpass bridge over Interstate 29 south of Fargo and just west of Hickson and Oxbow. The pouring of the bridge deck is complete.
David Samson/The Forum

Next year's work, which will be third and final year of the $67 million building project won't involve any detours or lane closures thanks to a four-lane bypass constructed last year.

As work continues on the cement guardrails this week, crews have finished paving roughly 1.25 miles of southbound lanes on I-29, part of the 4-mile stretch of interstate that will be raised.

Tooz said they expect to pave another 1.5 miles this year, with plans to complete surfacing next year in order to have the new raised interstate open by fall 2023.

The new stretch of interstate roadway will be about 4 to 10 feet higher than before. The 10-foot mark will take the freeway over the diversion's southern embankment, where a drainage ditch will force the construction of bridges for both the north and southbound lanes of the interstate.

Andersen said some of the earthwork has been completed and work will be starting on those bridges this month.

The project will keep the roadways out of the floodplain and allow them to remain open during major flooding.

ADVERTISEMENT

072522.N.FF.CONSTRUCTION12
Construction continues at a steady pace on the County Road 18 overpass bridge over Interstate 29 and surrounding area south of Fargo. Army Corps of Engineers Resident Engineer Mathew Andersen and Project Engineer Troy Tooz are pictured here walking down from the overpass bridge that was raised about three feet. This stretch of the bridge approach on County Road 18 will be rebuilt and freshly repaved.
David Samson/The Forum

MOORHEAD

CENTER AVENUE: All underground utilities have been completed and two of the three concrete lanes have been poured between Fourth Street and Sixth Street in front of the Moorhead Center Mall, which is Phase One of the project

The final lane should be paved this week along with curb and gutter, according to Moorhead City Engineer Clay Lexen.

"We’re still several weeks from opening that section of roadway as there will be installing of all new sidewalk on both sides of the street in that area," Lexen said.

Phase Two of the project involves reconstructing the road between Sixth Street and Eighth Street on the east end of the six-block project with work starting later in August, he said.

FARGO

34TH STREET SOUTH: Starting this Monday, July 25, north and southbound traffic will be reduced to one lane between 13th Avenue and 18th Avenue South to allow for street surface repairs. The road is expected to fully reopen by this Friday, July 29. Street parking will also be restricted.

FIRST AVENUE SOUTH: Westbound traffic will be closed between Fourth Street South and Broadway by Island Park and the YMCA so crews can place small cranes on the north side of the avenue in order to assemble a tower crane that is needed to complete the Bell Bank Tower project. The closure, starting this Monday, July 25, is expected to last three days.

MINNESOTA

STATE HIGHWAY 55: The Minnesota Department of Transportation has reopened the highway between Fairmount, North Dakota, and Highway 9 near Wendell, Minnesota, after resurfacing 22.5 miles of the roadway and replacing four box culverts.

ADVERTISEMENT

During the next couple of weeks, however, motorists may see intermittent lane closures while crews complete final striping and install signage along the entire project from Wendell to the Minnesota/North Dakota state line.

NORTH DAKOTA

HIGHWAY 11/18 IN LIDGERWOOD: A virtual public input meeting will be this Thursday, July 28, to receive comments on the highway project in the town.

The project consists of a new sidewalk and shared-use path and driveways within the existing right of way on the south side of the highway from Third Avenue Northwest to Wiley Avenue North.

A pre-recorded presentation and other materials will be available. It's not a live event. Go to dot.nd.gov and click on pubic meetings to view details.

072522.N.FF.CONSTRUCTION12
Work continues on the new raised County Road 18 overpass bridge over Interstate 29 south of Fargo and just west of Hickson and Oxbow. The interstate exit is closed while the project is ongoing. It's expected to reopen by the end of September.
David Samson/The Forum

What to read next
Breaking News
On Tuesday, investigators conducted an excavation in the 1000 block of 1st Ave. N. after receiving information that the body of Nikle may have been buried near the foundation of the residence when it was constructed.
Exclusive
In this episode of Dakota Spotlight, retired Bismarck Police Detective Bill Connor speaks frankly about the details of the case, still sharp in his memory, and his encounters with those connected to Michelle "Shelly" Julson as he re-investigated the case from 2005 to 2010.
Kristi Nikle's dad once lived on the street, and the teenager used to play with family and friends on the lot until the house was moved there.
Breaking News
Detectives would not discuss details of the case.